Kitchen Remodel - Day 5-7 (Week 2) Post 5/10


Before we move on to Week 2 (work days 5-9,) we brought the kids over to the house Friday evening to show them the progress...

11.7.11-11.9.11


It looked about the same at the end of day 6... not much had happened. Bruce, the electrician had come over for a couple of hours Tuesday and Wednesday and that's about it. I guess we got way too much accomplished last week. But, in hind sight, I am glad Sandra planned a couple of cushion days in, just in case there had been a surprise uncovered after the major demolition.
The beams were cut down to about 12'X16', the smallest we could safely go structurally.